Current Design Examples

BLANCHE42®
WWTP 170.000 P.E.
Erweiterung Wintergarten, 2018
Stahlbau, 2017
Architekturleistung HOAI, Lp. 1-9, 2016
MBR 3.500 P.E., 2015
Leachate Treatment Vietnam, 2014
Conservatory, 2012

WWTP Cost Estimation

View new graph

Project References

Please find selected references for completed projects that are demonstrating our service capabilities and quality of work for your first information.

 

The complete reference list is available upon request.

Please do not hesitate contating us by email for further details.

2023 Feasibility Study for 1,5 Mio. Population Equivalent (1000 MGL) - Central Asia

 

Conceptual Design of the WWTP and Sludge Treatment Facílities with Sludge Drying.

Process Design with MEICA Design, CAPEX/OPEX for optimized OPEX under max. heat/power recovery.

• WWTP design for Tertiary Wastewater Treatment (BNR)

Advanced Wastewater Treatment for enhanched pathogene removal

• Advanced Sludge Digestion with WAS disintegration

• Power recovery by CCHP for Trigeneration

• Thermal Sludge Treatment for Hygenisation with Mono-landfill                            

 

Feasibility Study for Cahul WWTP, Moldavia

October 2019 - April 2020

KfW: Water Supply and Sanitation in Cahul BMZ N° 201568344 and 201668904

Employer: FWT (www.fwt.fichtner.de)

Expert: Mathias Blanche (Wastewater & Sludge Process Expert)

 

 

 

 

 

Objective: Conceptual Design of the WWTP (32.000 P.E.), with MEICA Design, CAPEX/OPEX for minimized OPEX., incl. PID's and drawings, 3D presentations and workshops. Tender Design for FIDIC Yellow Book.

• WWTP design for Tertiary Wastewater Treatment (BNR) under Stage2

• Advanced sludge digestion

• Power recovery by CCHP for trigeneration

• Solar sludge drying with Mono-landfill                            

Feasibility Study for Cvetojevac WWTP in Kragujevac, Serbia

August 2018 - December 2019

SIDA: Environmental Infrastructure Support Programme - Phase 2 (EISP2)

Employer: Brooks Hannas & Partners Consortium, Belgrade

Expert: Mathias Blanche

 

 

 

 

 

Objective: Process/Hydraulic/MEICA design on conceptual design level for 2 variants (rehabilitation and new-built), incl. CAPEX/OPEX calculations, PID's and drawings, 3D presentations and workshops.

• WWTP design for Tertiary Wastewater Treatment (BNR)

• Advanced sludge digestion with WAS-disintegration

• Power recovery by CCHP for trigeneration

• Solar sludge drying with Mono-landfill                              PPT can be obtained after formal request!

Kragujevac PPT
MB6RS KG WW FS_WWTP Options Analysis -EN[...]
PDF-Dokument [36.2 MB]

National Sludge Management Strategy for Serbia

Nov. 2017 - March 2019

EuropeAid/132633/C/SER/Multi

Employer: ETI/expertise & advisors, Paris

Expert: Mathias Blanche

Objective: Sludge treatment, reuse and disposal process overview, definition of applicable sludge treatment concepts under consideration of current energy efficiency requirements and tendencies for reduction of specific sludge production. Reuse and disposal options considering latest developments for Phosphorous reclamation.

Draft action plan for implementation of sludge management concepts on regional level, cost estimation and proposal for implementation on short-/mid-/long-term horizon.

Final workshops and training seccions were held in Febr. 2019.

 

Training documents can be obtained after formal request!

NSMS Serbia
2 Process 2ndWS 20181206.pdf
PDF-Dokument [93.5 MB]

Tertiary Wastewater Treatment, Argentina

Sept. 2018 - March 2019

 

Situation: UV-Disinfection required for discharge of treated WWTP-effluent into lake. Bathing water requirements to be fullfilled due to tourism and fishing. 

Solution: Mico-Filtration plus UV-Disinfection, acc. EU/USEPA-Standards. Specific CAPEX 10 €/P.E. at OPEX 0,75 €/m3/yr.

Objective: Process design with design drawings and documentation for FIDIC YB Tender.

Process Expert: Mathias Blanche

Girne/Kyrenia WWTP - North Cyprus

August 2017

Extension of SBR Type WWTP for up to 80.000 P.E. (16 MLD)

Employer: Belediyesi Girne
Expert: Thomas Blanche

Objective: Headworks - Final design with Specifications and BoQ

Extra: Functional hydraulic model of PISTA grit chamber arrangement.

 

 

Completion of BLANCHE OFFICE Building - Steelworks for Stairs

August 2017

Velipoje WWTP - Phase III, Albania

March 2015 - May 2017

 

Project: EUROPEAID/133963/C/SER/AL

Employer: Eptisa SEE

Objective: Review and revision of Employers process design and documentation (detailed design drawings and BoQ) for Phase III - Extension of WWTP

Process Expert: Mathias Blanche

Song Trang (Waste Disposal) Leachate Treatment Plant

December 2015

 

Project: BMZ Project ID

Employer: Fichtner FWT, Freiburg

Objective: Review and revision of Employers process design and documentation (detailed design drawings and BoQ) for Constructed Wetland, 520 m3/d.

Process Expert: Mathias Blanche

Designer: Thomas Blanche

Kotor Bay, MNE

August - Dec. 2015

WATER SUPPLY AND SANITATION ADRIATIC COAST V – COMPONENT 2

Project: BMZ Project ID 2015 67 817

Employer: Fichtner FWT, Freiburg

Objective: Process design and documentation for 3 WWTP's in Kotor Bay

with Variant Analysis for SBR/MBR and MBBR/IFAS process.

Process, M&E Expert: Mathias Blanche

Architectural & Civil Design: Thomas Blanche

Girne/Kyrenia WWTP - North Cyprus

Oct/Nov. 2015

Extension of SBR Type WWTP for up to 80.000 P.E. (16 MLD)

Employer: Belediyesi Girne
Expert: Mathias Blanche

Objective: Implementation concept for extension and upgrade of the existing WWTP for maximum treatment capacity on site.

 

March 2015 - Industrial Pre-Treatment - Turkey

Works Supervision CWMC MARISCINA - Solid Waste Disposal - Croatia

March 2014 - Oct. 2015

Construction works stated in June 2012

EuropeAid-IPA

MBR Type Leachate WWTP

Client: ECOPLUS, Riejka

Employer: EPTISA Adria d.o.o., Zagreb

Expert: Mathias Blanche

Objective: Works Supervision of WWTP, FIDIC Yellow Book

WWTP SLAVONSKI BROD, Croatia

October 2011 - October 2015

Construction works stated in June 2012

EuropeAid-IPA 2008HR16IPR003/1

SBR Type WWTP for 60.000/80.000 P.E. with Sludge Digestion

Client: HR_Voda, Zagreb

Employer: EPTISA SEE, Belgrade

Expert: Mathias Blanche

Objective: Works Supervision, FIDIC Yellow Book

Velipoje WWTP, Albania - Phase I&II

March 2015

Construction Works in 2012

EuropeAid/128827/C/SER/AL

SBR Type WWTP for 18.000 P.E.

Employer: EPTISA Adria d.o.o., Zagreb

Expert: Mathias Blanche

Objective: Works Supervision, FIDIC Red Book

Feacal Sludge Treatment - Vanuatu

October 2014

Project: Port Vila Urban Development Project

Employer: RPSA Limited (Roughton International)

Process: Mathias Blanche

Designer: Thomas Blanche

Position: Drainage/Sanitation Support Engineer in Vanuatu

Objective: Tender Design.

GIS for Indochina

March 2014: Available GIS Maps

ePaper
GIS Datasets available for Myanmar, Thailand, Cambodia, Vietnam and Laos

Expert: Thomas Blanche
Objective: GIS Study and Map-Sets

Teilen:

Nizip WWTP

Febr. 2014 - Dec. 2015

Flow Chart

Phase 1 with 114.000 P.E. with

Tertiary Treatment with Sludge Digestion

EuropeAid:

Client:

Employer: Fichtner-FWT, Freiburg

Objective: Process design, FIDIC Yellow Book Tender

MAPUTO WATER SUPPLY - PROJECT

October 2013 - January 2014

Feasibility Study

Employer: EGIS International, Nairobi

Expert: Thomas Blanche

Objective: GIS Study and Map-Sets, Hydrological and Topographical Analysis.

WWTP SISAK, Croatia

EuropeAid/132999/D/SER/HR

Conventional Type WWTP for 60.000 P.E. with

Simultaneous Aerobic Sludge Stabilization

Client: HR_Voda, Zagreb

Employer: EPTISA Adria d.o.o, Zagreb

Objective: Works Supervision, FIDIC Yellow Book

SEEM for Process Design Optimization, India

November - December 2012

Flow Chart - SEEM

SBR Type WWTP design capacity

15 MLD (110.000 P.E.) and

20 MLD (140.000 P.E.)

Employer: Fichtner FWT, Freiburg

Expert: Mathias Blanche

Objective: Process Design Assessment,

Energy Efficieny Analysis with SEEM,

Redesign for Power Generation.

WWTP PLAV, Montenegro

April 2012 - February 2013

Visualization Draft Layout of WWTP

Capacity: 18.000 P.E.

Client: ECD Montenegro

Employer: Alternative Consulting, Belgrade

Expert: Mathias Blanche

Objective: Preliminary design for the construction of waste water treatment plant and sewerage network in the Municipality of Plav and the urban settlement of Gusinje, Request N° 2011/279306-1

SBR Type WWTP with Main Pumping Station

 

Details

WWTP BIHAC, Bosnia-Hercegovina

October 2011 - March 2012

Capacity: 60.000 P.E.

Client/IFI: KfW Frankfurt

Employer: Fichtner FWT, Freiburg

Objective: Conceptual design, incl. designers cost estimate and least-cost-analysis.

Expert: Mathias Blanche

WWTP Sipopo, Equatorial-Guinea

July 2010 - October 2012

WWTP SIPOPO: 12.000 P.E. MBR

CNP-Removal acc. 91/271/EEC & 2006/7/EC.

MBR system with simultaneous sludge stabilisation

and sludge dewatering.

Estimated budget 5 Mio. EUR.



Final design, incl. hydraulic & process design; architectural, civil and mechanical design; co-ordination of electrical and SCADA design.

Drawings, Spec's and BoQ's for civil and M&E works for tendering acc. German Standards (analogous Red Book).

Expert: Mathias Blanche

Cooperation: BitControl (Electrical and SCADA Design)

Kosovo South-West

April 2011 - August 2011

WWTP PRIZREN: 100.000 P.E.

WWTP PEJA: 80.000 P.E.

WWTP GJAKOVA: 50.000 P.E.

Client/IFI: KfW Frankfurt

Employer: Fichtner FWT, Freiburg

Objective: Conceptual design, incl. designers cost estimate and least-cost-analysis.

Expert: Mathias Blanche

WWTP Constanta, Romania

August 2007 - December 2011

Capacity: 355.000 P.E.

Client: CFCU, Bucharest & RAJA, Constanta

Employer: IGIP mbH, Darmstadt

Objective: Works Supervision, FIDIC Yellow Book

Expert: Mathias Blanche

Fotos ©PASSAVANT ROEDIGER ANLAGENBAU GmbH, Hanau, Germany

WWTP Ramnicu Valcea, Romania

Jule 2008 - July 2011

Capacity: 130.000 P.E.

Client: CFCU, Bucharest

Employer: EPTISA Proyectos Internacionales S.A.

Objective: Works Supervision, FIDIC Yellow Book

Expert: Mathias Blanche

WWTP Gussev/Gumbinnen, Russia

Mai 2005 - October 2005

Capacity: 25.000 P.E.

Client: Oblast Kaliningrad, EU-Delegation

Employer: MVV Consulting GmbH, Mannheim

Objective: Conceptual Design for 4 WWTP's, incl. Cost Estimates.

FIDIC Yellow Book Tender Final Design (Vol. 3-5).

Expert: Mathias Blanche

BCM Tender Drawings (FIDIC Yellow Book)
WWTP Gussev.pdf
PDF-Dokument [7.4 MB]

WWTP Kyrenia/Girne, North-Cyprus

July 2004 - November 2010

Opening Ceremony 2010

Capacity: 15.000 P.E.

General Consulting Services during said period to City of Girne and UNDP.

Objective: Consultancy Services and Process Assessment; Feasibility Study for rehabilitation or extension of the WWTP up to 15,000 P.E. Tender design. Tendering (RFP) & Tender Evaluation, acc. UNCRITAL.

Client: Municipality of Girne/Kirenia, North-Cyprus

Employer: UNDP Nicosia 2004 and Municipality of Girne 2006 - 2010

Expert: Mathias Blanche

Senior Supervisor for WWTP Kyrenia Rehabilitation & Extension.

Mila Mia Haspolat Tender Evaluation

Capacity: 270.000 P.E.

Client: Sewerage Board of Nicosia, Cyprus

Employer: UNDP PFF Nicosia

Expert: Mathias Blanche

Objective: Tender Evaluation for MBR type WWTP 

General Consulting Services to UNDP for Mila Mia Haspolat WWTP.

 

WWTP Sivas, Turkey

November 2005 - June 2006

Capacity: 140.000 P.E.

Client: KfW, Frankfurt and Citiy of Sivas

Employer: H.P. Gauff Ingenieure GmbH & Co. KG -JBG-, Frankfurt

Objective: Review of conceptual design and elaboration of Volumes 3-5 for FIDIC Yellow Book (Plant and Design, Build). Backstopping and assistance during Tender Period & Evaluation.

Expert: Mathias Blanche

WWTP Corlu, Turkey

October 2003 – December 2004

Capacity: 40.000 m3/d (appr. 1 Mio. P.E.)

Client: Corlu Organized Industrial Zone

Employer: MVV Consulting GmbH, Mannheim

Objective: Coordination of the team of experts for process and civil design approval, incl. design & safety evaluation (HAZOP). Assistance to the client in all technical aspects (i.e. hydraulic calculations, dimensioning of equipment).

Expert: Mathias Blanche

WWTP ABUJA, Nigeria

Period 1999 - 2001

Capacity: 700.000 P.E.

Assignment: Sub-consultant

Scope: Final Design (Process/Hydraulic/Meica Design, Detailed Design Drawings, BoQ (acc. German Standards), coordination specialized experts.

Expert1: Mathias Blanche (Process, MEICA)

Expert2: Thomas Blanche (Architectural & Detailed Design)

WWTP Tolmin, Slovenia

Period: 2000

Capacity: 8.000 P.E.

Assignment: Sub-consultant for OMS Kläranlagen GmbH

Scope: Preliminary Design (Process/Hydraulic/Meica Design, Drawings, BoQ

Expert1: Mathias Blanche (Process, MEICA)

Expert2: Thomas Blanche (Architectural & Detailed Design)

WWTP Al Bireh (Rahmalla), Palestine

1997 - 2000

Capacity: 50.000 P.E.

Client: KfW Frankfurt

Employer: PASSAVANT-WERKE AG

Expert1: Mathias Blanche (Process, MEICA)

Expert2: Thomas Blanche (Architectural & Detailed Design, PM)

1. Tender Proposal (FIDIC P&DB); incl. Architectural  Design, Process Design, M&E and Hydraulic Engineering, Cost Estimates and Tendering Assistance.

2. Final & Detailed Design, incl. Architectural, Hydraulic & Process Design, Mechanical Engineering and co-ordination of special designers for Electrical & SCADA as well as Structural Engineering, support of local designers.

3. Project & Site Management; Documentation (O&M, As-built).

WWTP Hahnstätten, Germany

Period

Druckversion | Sitemap